Phase III Ship Loading Dock and CBU Receiving - Convent, La.
STATUS
Substantial Completion February 28, 2018
OWNER
ZEN-NOH Grain Corporation
CONTRACT TYPE
Design-Build / EPC
AWARDS
2017 GEAPS Safety Award, for completing 252,626 working hours without a serious injury during 2017
Ibberson was awarded this design-build contract to provide design, engineering, procurement, construction, and start-up and testing support for a new ship loading dock and barge slip.
The scope of work includes design engineering (civil, structural, mechanical, and electrical) of a complete dock structure, including ship berthing capability for Post-Panamax size vessels and a dual barge unloading slip. The dock structure connects to the existing dock and is designed to accommodate future ship loading capabilities.
The high-speed barge unloading capabilities are designed to unload barges with a 120,000-BPH continuous barge unloader. The barge slip is a dual design to accommodate two barges at one time.
The high speed over water/land belt conveying system is designed to transfer products at a rate of 120,000 BPH from barges to a new scale tower or transfer products directly to the existing ship loading system.
The high speed over land belt conveying system is designed to transfer products at a rate of 120,000 BPH from the scale tower to the existing concrete storage tanks for storage.
The entire product transfer system includes a state-of-the art dust collection system designed to control dust at all critical transfer points.