Dairy Nugget Extrusion Plant Expansion - Russell, Kan.
START DATE
December 2006
COMPLETION DATE
December 2010
OWNER
Land O’Lakes Purina Feed LLC
CONTRACT TYPE
Design-Build / EPC
CONTRACT VALUE
$12,695,661
MAN-HOURS
47,601
AWARDS
Eagle Award - 2009 ABC Minnesota
Ibberson was awarded the contract to provide design and construction services for the new manufacturing capabilities on a new product in its extensive line of high-end animal feed products. It involved major modifications and expansion of an existing feed extrusion plant facility.
The project included fast-track design-build construction by Ibberson and its subcontractors; demolition and removal of existing equipment; site grading modifications and new railroad spur track installation; new platform truck scale; new rail and truck bulk liquid ingredient unloading and storage systems; new grain and meal processing systems; new extruder cooler; new process tower addition and process building modifications; new finished product transfer systems to bulk loadout; new rail and truck finished product bulk load out facilities and building; new and expanded process control systems hardware and programming; new and expanded process mechanical equipment and piping systems installation; and new and expanded power, control and electrical hardware and wiring installation.